Bluff Community Center Playground Sidewalk Perimeter Construction
Status: Out for Bid
Bid Holders List
Schedule:
| Project Milestone | Date |
| RFP Release | Tuesday, January 6, 2026 |
| Mandatory Virtual and In-Person Pre-Bid Meeting | Wednesday, January 14, 2026 @ 1:00pm MST at the Bluff Community Center Link: https://zoom.us/j/96486762629 |
| Last Day to Ask Questions | Monday, January 19, 2026 @ 5:00pm MST |
| Proposal Submission Due | Tuesday, January 27, 2026 @ 5:00pm MST |
| Contractor Selected | Week of February 2 – February 6, 2026 |
| Sidewalk Project Start | As soon after selection as possible |
| Estimated Completion | March 4, 2026 |
Energy Efficiency Lighting Retrofit Project
Awarded to: UltraLights Lighting
Status: In Progress
Multi-Court and Playground Project
Awarded to: Garrett Parks & Play
Status: In Progress